100% Money Back Guarantee

2Pass4sure has an unprecedented 99.6% first time pass rate among our customers. We're so confident of our products that we provide no hassle product exchange.

  • Best exam practice material
  • Three formats are optional
  • 10 years of excellence
  • 365 Days Free Updates
  • Learn anywhere, anytime
  • 100% Safe shopping experience

74-343 Online Test Engine

  • Online Tool, Convenient, easy to study.
  • Instant Online Access 74-343 Dumps
  • Supports All Web Browsers
  • 74-343 Practice Online Anytime
  • Test History and Performance Review
  • Supports Windows / Mac / Android / iOS, etc.
  • Try Online Engine Demo
  • Total Questions: 110
  • Updated on: Sep 01, 2026
  • Price: $69.00

74-343 Desktop Test Engine

  • Installable Software Application
  • Simulates Real 74-343 Exam Environment
  • Builds 74-343 Exam Confidence
  • Supports MS Operating System
  • Two Modes For 74-343 Practice
  • Practice Offline Anytime
  • Software Screenshots
  • Total Questions: 110
  • Updated on: Sep 01, 2026
  • Price: $69.00

74-343 PDF Practice Q&A's

  • Printable 74-343 PDF Format
  • Prepared by Microsoft Experts
  • Instant Access to Download 74-343 PDF
  • Study Anywhere, Anytime
  • 365 Days Free Updates
  • Free 74-343 PDF Demo Available
  • Download Q&A's Demo
  • Total Questions: 110
  • Updated on: Sep 01, 2026
  • Price: $69.00

In 2026, failing the Microsoft Managing Projects with Microsoft Project 2013 exam means paying the full registration fee a second time — plus weeks of lost momentum. The 110 practice questions in 2Pass4sure's 74-343 package are designed to help you get it done on the first attempt.

Microsoft 74-343 Exam Overview:

Certification Vendor:Microsoft
Exam Name:Managing Projects with Microsoft Project 2013
Exam Number:74-343
Passing Score:700/1000
Exam Duration:50 minutes
Available Languages:Japanese, German, English, Spanish, French, Chinese (Simplified)
Exam Price:Approximately USD 100 (varies by region)
Related Certifications:Microsoft Office Specialist (MOS) Project 2013 Expert
Real Exam Qty:20-35 tasks (performance-based)
Certificate Validity Period:Does not expire
Exam Format:Task-driven assessment, Lab simulation, Performance-based
Recommended Training:Microsoft Learn - Project training
Exam Registration:Microsoft Certification Portal
Sample Questions: DOWNLOAD DEMO
Exam Way:Available via authorized test centers or online proctored delivery (where supported)
Pre Condition:No formal prerequisites required, recommended familiarity with Microsoft Project 2013
Official Syllabus URL:https://learn.microsoft.com/en-us/credentials/

Microsoft 74-343 Exam Syllabus Topics:

SectionObjectives
Topic 1: Managing Resources- Resource allocation and optimization
  • 1. Resolve resource overallocations
    • 2. Assign work resources
      Topic 2: Creating and Managing a Project- Project file creation and configuration
      • 1. Set up a new project file
        • 2. Define project start and finish dates
          Topic 3: Managing Tasks- Task creation and structure
          • 1. Define task dependencies
            • 2. Work with task constraints
              • 3. Create tasks and milestones
                Topic 4: Tracking Project Progress- Monitoring and updating progress
                • 1. Set baselines
                  • 2. Update task progress
                    • 3. Compare planned vs actual progress
                      Topic 5: Reporting and Communication- Project reporting tools
                      • 1. Generate built-in reports
                        • 2. Visualize project data

                          Microsoft 74-343 Exam FAQ — What Candidates Ask Most

                          The 74-343 exam is the official Microsoft exam for Microsoft Managing Projects with Microsoft Project 2013. Passing it earns you the Microsoft Office Specialist (MOS) - Project 2013 credential, which sits at the Associate level. It is also connected to Microsoft Office Specialist (MOS) Project 2013 Expert, so what you learn carries over if you plan to pursue those paths as well. Employers treat the certification as verified proof of skill, which is why structured preparation with 2Pass4sure's practice questions pays off.

                          The 74-343 exam contains 20-35 tasks (performance-based) questions, and the time limit is 50 minutes. Translate that into a pacing plan before exam day: know roughly how long you can afford per item, flag anything that stalls you, and circle back at the end instead of burning minutes. Two or three full timed sessions in 2Pass4sure's test engine will teach you that rhythm far better than untimed reading ever will.

                          The passing score for the 74-343 exam is 700/1000, and the official registration fee is Approximately USD 100 (varies by region). Remember that a failed attempt means paying that fee again in full for a retake, so treat self-assessment as part of the budget: run 2Pass4sure's practice questions under timed conditions and only book your seat once your scores sit comfortably above the passing bar.

                          No formal prerequisites required, recommended familiarity with Microsoft Project 2013 Eligibility details can change, so before you register, confirm the current requirements on the official exam page: https://learn.microsoft.com/en-us/credentials/.

                          You can book the 74-343 exam through the official registration channels below:

                          Exam delivery method: Available via authorized test centers or online proctored delivery (where supported).

                          Microsoft points candidates to the following official training options:

                          Once the coursework has built your foundation, the fastest way to turn theory into exam readiness is drilling with 2Pass4sure's 110 practice questions for the Microsoft Managing Projects with Microsoft Project 2013 exam.

                          Yes. 2Pass4sure offers a free PDF demo of the Microsoft Managing Projects with Microsoft Project 2013 practice questions on the samples page, so you can judge the format and quality yourself before paying anything. Every purchase also includes 365 days of free updates, and after the product expires you can extend the update service at a 50% discount from within your member zone.

                          If you take the corresponding exam within 60 days of purchase and do not pass, 2Pass4sure backs you with a 100% money-back guarantee. To claim it, submit a scanned copy of your exam enrollment slip together with your official Score Report PDF within 2 days of the exam, and the refund is processed within 7 days. The guarantee does not apply to attempts made within the first 3 days after purchase, to products downloaded without actually sitting the exam, or to free materials and expired orders, and the candidate name must match the payer's name. If you would rather have study material than money, you can instead exchange for two additional exam products of equal value, free of charge, while keeping the update service on your original purchase. Delivery itself is instant: your download is available right after payment and a copy reaches your mailbox within one minute — if nothing arrives within 2 hours, contact customer service. You may install the product on as many computers as you need.

                          The official Microsoft Managing Projects with Microsoft Project 2013 blueprint is organized into 5 domains. The leading areas are:

                          • Tracking Project Progress
                          • Managing Resources
                          • Reporting and Communication

                          For the complete domain-by-domain breakdown with every subtopic, see the Exam Topics outline above.

                          Microsoft Managing Projects with Microsoft Project 2013 Sample Questions:

                          Question 1

                          Your company uses Project Standard 2013 to track project progress.
                          You need to accurately calculate cost performance index (CPI) as a health indicator.
                          Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

                          A. Ensure there is a value in the Status Date field.
                          B. Ensure there is a value in the Standard Rate field.
                          C. Level resources within available slack.
                          D. Ensure Task Dependencies exist in the schedule.
                          E. Enter actual progress information.


                          Question 2

                          You are a project manager who uses Project Professional 2013.
                          You are creating a project with several phases. Your customer requires the delivery phase of the project to start on July 1 and to finish within four weeks. The delivery phase includes a summary task, which consists of five separate sub tasks.
                          You need to monitor this phase closely to ensure that it does not overrun.
                          What should you do?

                          A. Create a manually scheduled summary task of 20 days. Create a deadline for the task which is set to July 29. Monitor the progress of the summary task against the deadline.
                          B. Create a manually scheduled summary task of 20 days. Enter a Finish No Later Than constraint which is set to July 29.
                          C. Create an automatically scheduled summary task of 20 days. Set the start date to July 1.
                          D. Create an automatically scheduled summary task of 20 days. Set the finish date to July 29.
                          E. Set a deadline date for the automatically scheduled summary task for four weeks after July 1. Monitor the progress of the summary task against the deadline.


                          Question 3

                          You are a resource manager who uses Project Standard 2013.
                          You manage all of your resources in a single plan, which acts as a Shared Resource Pool for other projects in your organization. Each resource needs to pass an annual exam in order to work on construction sites.
                          You need to set up a method that allows you to pick the renewal month for each resource.
                          What should you do?

                          A. Rename the Resource Date1 Custom field to Exam Expiration Date. Create a Lookup table with values containing the last date of each month. Select the correct expiration date for each exam.
                          B. Rename the Resource Text1 Custom field to Exam Expiration Date. Enter the month when the exam expires. Select the correct expiration date for each resource.
                          C. Use the Organizer to copy the ResourceFinish1 Custom field from the Global.mpt.
                          Select the correct expiration date for each resource.
                          D. Rename the Resource Flag1 Custom field to Exam Expired Date. Enter the expiration dates into a Lookup table. Select the correct expiration date for each resource.
                          E. Rename the Resource Month1 Custom field to Exam Expiration Date. Create a Lookup table with monthly values. Select the correct expiration month for each exam.


                          Question 4

                          You are a project manager who uses Microsoft project.
                          Your manager wants you to plan an office move. You have a project schedule from a prior office move named OfficeMove.mpp.
                          You need to create a new project schedule based on the old project schedule by performing the fewest steps possible.
                          What should you do?

                          A. Open the old OfficeMove.mpp file and save the file using a new file name. Then, enter the project name in the Project Summary task. Set all tasks to zero percent complete.
                          B. Open the Old OfficeMove.mpp file and change the project start date and project title.
                          Clear the baseline and save the file using the current project name.
                          C. Open the old OfficeMove.mpp file and save the file using a new file name. Clear the baseline and set all tasks to zero percent complete.
                          D. Open the old OfficeMove.mpp file and save the file as Project template file. Create a new project using the template.


                          Question 5

                          You are a Project Manager who uses Project Professional 2013.
                          You manage a critical project, which is synchronized with a Microsoft SharePoint Task List.
                          One of your team members has changed a task priority to High in SharePoint, and you do not see the changed data in Project Professional 2013.
                          What should you do?

                          A. Use the Task Information box to copy the Priority field from the SharePoint Task List.
                          B. Use the Organizer to copy the Priority field from the SharePoint Task List.
                          C. Map the Priority field from SharePoint to Project by using Project, Custom Fields, Import Field.
                          D. Map the Priority field from SharePoint to Project by using File, Info.


                          Solutions:

                          Question 1
                          Answer: A,B,E
                          Question 2
                          Answer: E
                          Question 3
                          Answer: A
                          Question 4
                          Answer: C
                          Question 5
                          Answer: D

                          524 Customer ReviewsCustomers Feedback (* Some similar or old comments have been hidden.)

                          Good 74-343 products! It's quite cheaper than i bought before.

                          Jacob

                          Jacob     5 star  

                          Questions and answers in the pdf file were almost the same as the real exam. Thank you for this great work 2Pass4sure. I suggest all taking the 74-343 exam to prepare from this pdf file. I got 98% marks.

                          Gustave

                          Gustave     4 star  

                          I suggest everyone buy the 2Pass4sure pdf bundle with practise exam. It further increases your chances of scoring well in the exam. I passed the 74-343 exam with 96% marks today.

                          Donahue

                          Donahue     5 star  

                          I am sure that when you have 74-343 exam engine then 74-343 exam would become a piece of cake for you.

                          Marico

                          Marico     5 star  

                          Great value for money spent. Practised a lot on the exam testing software by 2Pass4sure. Real exam became much easier with it. Scored 95% marks in the 74-343 exam.

                          Montague

                          Montague     5 star  

                          I cleared my 74-343 exam with 96%. Feeling relaxed!!Thanks a lot!!!I will be back if i need other exam study material.

                          Joa

                          Joa     4.5 star  

                          Today i take part in 74-343 exam,the result let me exciting,thank you so much.

                          Norman

                          Norman     4 star  

                          2Pass4sure is the best site for learning and passing the 74-343 exam. I have gotten the certification now. I will buy the other exam materials only from 2Pass4sure later on.

                          Michael

                          Michael     4 star  

                          LEAVE A REPLY

                          Your email address will not be published. Required fields are marked *

                          Instant Download 74-343

                          After Payment, our system will send you the products you purchase in mailbox in a minute after payment. If not received within 2 hours, please contact us.

                          365 Days Free Updates

                          Free update is available within 365 days after your purchase. After 365 days, you will get 50% discounts for updating.

                          Porto

                          Money Back Guarantee

                          Full refund if you fail the corresponding exam in 60 days after purchasing. And Free get any another product.

                          Security & Privacy

                          We respect customer privacy. We use McAfee's security service to provide you with utmost security for your personal information & peace of mind.