NEW QUESTION # 28
Which kind of environment must the Scrum Master foster? Select three answers
- A. A Product Owner organize the work for a complex problem into a Sprint Backlog
- B. The Scrum Team and its stakeholders inspect the results and adjust for the next Sprint
- C. The Scrum Team turns a selection of the work into an Increment of value during a Sprint
- D. The Scrum Team turns an increment of value into a working environment during a Sprint
- E. The Scrum Team and its stakeholders plan the work for the next Sprint
- F. A Product Owner orders the work for a complex problem into a Product Backlog
Answer: B,C,F
NEW QUESTION # 29
Only one increment can be created in a Sprint
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 30
You are an Agile Coach. In the middle of the Sprint, the Lead Engineer calls you and informs you that due to a health problem, he will not be available for the rest of the Sprint.
What should you do?
- A. Postpone the release date.
- B. Ask the team how much of the planned work can be done and if necessary, negotiate the scope with the Product Owner.
- C. Request a new lead engineer for your team.
- D. Ask the team how much of the planned work can be done and extend the Sprint if necessary.
- E. Promote another Developer to Lead Engineer for this Sprint.
- F. Ask Developers to work overtime.
Answer: B
NEW QUESTION # 31
An organization has many Agile teams working on different products. How can managers understand the status of each team? (choose the best answer)
- A. Standardize story point estimation across teams so that team velocity can be compared.
- B. Ask the teams to show progress toward the Product Goal at least every calendar month.
- C. Have the team create a detailed forecast for their work, then track plan versus actuals.
- D. Instruct each team to fill out a common status reporting dashboard to provide information that can be shared with stakeholders.
Answer: B
Explanation:
In Agile, progress is measured by value delivered toward the Product Goal, not by tracking detailed forecasts or comparing velocities. Asking teams to demonstrate their progress toward the Product Goal allows stakeholders to see meaningful progress without introducing unnecessary bureaucracy.
NEW QUESTION # 32
What is a hypothesis?
- A. A proposed explanation for some observation that has not yet been proven
- B. A test that is designed to prove or reject something
- C. A proven explanation that needs to be implemented
- D. A test for a feature that provides value
- E. A test to measure the value of something
Answer: A
NEW QUESTION # 33
In large Scrum Teams, there may be two or more Product Owners
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 34
A software development company that uses the waterfall software development approach realizes that the cost of development of a Project has been more than what they had initially planned. The Management believes that adopting an Agile approach will help to reduce cost. Should they adopt Agile and an approach to reduce cost?
- A. YES
- B. NO
Answer: B
NEW QUESTION # 35
How do organizations move from their Current State toward their Next Target Goal?
- A. With the Development cycle
- B. With the experiment loop
- C. Using the three pillars of empirical process control
Answer: B
NEW QUESTION # 36
What is called the measure of the amount of time from when an idea is proposed or a hypothesis is formed until a customer can benefit from that idea?
- A. Development Time.
- B. Customer Cycle Time.
- C. Lead Time.
- D. Time to Learn.
- E. Implementation Time.
- F. Time to Pivot.
Answer: C
NEW QUESTION # 37
The Sprint Review is the only time during the Sprint that Stakeholders can meet with the Scrum Team.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 38
What is the main direct benefit of an Agile approach?
- A. Improve team structure
- B. Cost reduction
- C. Flat management structure
- D. Deliver more value
Answer: D
NEW QUESTION # 39
What is identified by the end of the Sprint Retrospective?
- A. The most important problems
- B. The most helpful changes to improve its effectiveness
- C. Improvements for the company
- D. The most important features
Answer: B
NEW QUESTION # 40
The first step in the journey toward a Strategic Goal is understanding your Current State.
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION # 41
What would be the effect of Artifacts with low transparency?
- A. None
- B. better results
- C. The Scrum Master will be disappointed
- D. Not all artifacts must be transparent
- E. Can lead to decisions that diminish the value and increase risk
Answer: E
NEW QUESTION # 42
What should you avoid as an Agile Team leader?
- A. Rewarding individual goals at the expense of project goals.
- B. Finding out what motivates the team members individually.
- C. Collaborate in setting the Product Goals.
- D. Prioritizing team goals over individual goals.
Answer: A
NEW QUESTION # 43
A member of a Scrum Team is interested in understanding the organization's ability to deliver value. She asks if he can explain what the Time to Market Key Value Area (T2M) can reveal.
What would you answer?
- A. The average velocity across all Scrum Teams in the organization.
- B. The organization's ability to quickly deliver new capabilities, services, or products
- C. The average time required to perform a release.
- D. How quickly the organization can develop Products.
Answer: B
NEW QUESTION # 44
You are a Product Owner. The Developers are close to the end of a Sprint and ask you for 3 extra days to complete their work. They feel that if they do not get the extra time, they might look bad in front of stakeholders, who are already skeptical of using an agile approach. What should you do? (choose the best answer)
- A. Ask the Developers to commit to what was agreed and find a solution for the problem.
- B. Ask the Developers to work longer hours to meet their goal.
- C. Agree to extend the Sprint but ask the team to be more realistic when they plan Sprints in the future.
- D. Cut back on testing, or leave some items incomplete, so long as the Developers can "substantially meet" their goal.
- E. Do not extend the Sprint and stick to the original timebox. Work with the stakeholders to explain why transparency and openness are important.
Answer: E
Explanation:
In Scrum, the Sprint timebox is sacred. Extending it undermines the concept of commitment and predictability. Instead, use this as an opportunity to promote transparency and openness by explaining to stakeholders the value of inspecting and adapting based on the current progress. Thisapproach strengthens trust in the Agile process.
NEW QUESTION # 45
......