NEW QUESTION 20
Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the customer sets a planning time fence with firming type 1 in the material master.
How is the resulting firming interval specified in this scenario?
- A. It is predefined in Customizing.
- B. By the planning time fence from the material master
- C. By the manual firming date
- D. By the firming mechanism with the longer firming interval
Answer: D
NEW QUESTION 21
When testing requirements planning in plant 1000, you receive the error message displayed below. Large numbers of materials are already available in plant 1000. As a first step in solving the problem, you activate requirements planning in the Customizing for plant 1000.
What further tasks do you perform before you can use requirements planning in plant 1000 in SAP ECC?
- A. Set up the planning files in Customizing and specify the plant parameters for plant 1000 in Customizing of the MRP group.
- B. Activate requirements planning in Customizing for MRP areas in plant 1000 and specify the plant parameters for plant 1000 in the MRP views in material master.
- C. Set up the planning file in Customizing and specify the plant parameters for plant 1000 in the MRP views in material master.
- D. Set up the planning file in Customizing and specify the plant parameters for plant 1000 in Customizing.
Answer: D
NEW QUESTION 22
In which of the following objects can you activate back flushing for production orders? (Choose three)
- A. Routing
- B. Material master (component)
- C. Production scheduling profile
- D. Work center
- E. Material master (finished product)
Answer: A,B,D
NEW QUESTION 23
Which of the following organizational efforts can be minimized using the KANBAN procedure?
- A. Effort for master data maintenance
- B. Effort for material staging
- C. Effort for capacity planning
- D. Effort for Sales and Operations Planning (SOP)
Answer: B
NEW QUESTION 24
The final assembly of a finished product should only be triggered when a customer order arrives.
Which planning strategy for the finished product do you use?
- A. Planning with make-to-stock (strategy 10)
- B. Planning at the assembly level (strategy 70)
- C. Planning with final assembly (strategy 40)
- D. Planning without final assembly (strategy 50)
Answer: D
NEW QUESTION 25
Which repetitive manufacturing options can you use to carry out line loading in the SAP ECC system, and thus generate run schedule quantities (RSQ) from normal planned orders? (Choose three)
- A. Automatic selection of the production version in material requirements planning (MRP) using the selection methods setting
- B. Automatic selection of the production version by applying quota arrangement records in material requirements planning (MRP)
- C. A planning algorithm from capacity planning
- D. Manual assignment of planned production quantities in a planning table
- E. Automatic selection of the production line assigned to the MRP group used during material requirements planning (MRP)
Answer: A,B,D
NEW QUESTION 26
Which of the following properties applies to multi-site planning in SAP ECC?
- A. Both withdrawal from an alternative plant and stock transfer from another plant are defined via special procurement keys.
- B. When using one-step stock transfer posting, transfer stock is created in the receiving plant.
- C. The use of "scope of planning" is always mandatory for multi-site planning.
- D. Multi-site planning can be activated using the corresponding planning strategy.
Answer: A
NEW QUESTION 27
An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon is to be set equally for all materials by default.
However, some materials are to be given a different planning horizon.
What procedure would you recommend to the project team for setting the planning horizon on the system side?
- A. The planning horizon is set in Customizing using the plant parameter setting and variant entries are assigned via the MRP groups for the materials in question.
- B. The planning horizon is set in the MRP groups in Customizing and variant entries are assigned via the plant parameter settings.
- C. The planning horizon is set in the plant parameters in Customizing and variant entries are stored in the material masters for the materials in question.
- D. The planning horizon is set in the MRP groups in Customizing and the variant values are stored in the material masters for the materials in question.
Answer: A
NEW QUESTION 28
Which of the following functions does SAP Supply Chain Management (SCM) offer?
- A. Product development, safety, quality, and maintenance
- B. Communication with customers through different interaction channels
- C. Planning of supply chains across company boundaries
- D. Optimization of the procurement strategy with the supplier pool
Answer: C
NEW QUESTION 29
What master data do you need for material replenishment using the KANBAN procedure? (Choose two)
- A. Control cycle
- B. Production supply area
- C. Product cost collector
- D. Production version
- E. Rate routing
Answer: A,B
NEW QUESTION 30
Which of the following features are offered by MRP areas in SAP ECC? (Choose two)
- A. A storage location may be assigned to different MRP areas.
- B. Make-to-order production is supported by storage location MRP areas.
- C. Subcontracting is supported by MRP areas.
- D. An MRP area may include different storage locations.
Answer: C,D
NEW QUESTION 31
What do you have to consider regarding lot size procedures?
- A. If a long-term lot size is used, procurement is conducted with a long-term perspective.
- B. The procurement quantity of a lot size procedure can be specified using a safety time period profile.
- C. If a make-to-order production strategy is used, only the lot-for-lot (exact) lot size can be applied.
- D. The lot size quantity can be influenced using a minimum lot size and the rounding profile.
Answer: D
NEW QUESTION 32
Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?
- A. Activate the availability check and assign an overall profile in the production scheduling profile.
- B. Set the finite scheduling indicator and assign a checking rule in the work center for the operation to be checked.
- C. Activate the availability check and assign an overall profile in the checking control of the order type / plant combination.
- D. Assign an appropriate availability checking rule to the material master for the product.
Answer: C
NEW QUESTION 33
You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you want to use a second sequence on other work centers for operations 30 and 40.
Which sequence category do you use to create the second sequence in the system?
- A. Finish-start relationship
- B. Parallel sequence
- C. Alternative sequence
- D. Standard sequence
Answer: C
NEW QUESTION 34
Which of the following situations occur when a production order is set to Technically Complete (TECO)?
(Choose three.)
- A. Purchase orders for external operations or non-stock materials are deleted.
- B. Reservations are deleted.
- C. The order is no longer relevant for Material Requirements Planning.
- D. The order and its operations receive the system status Locked (LKD).
- E. Capacity requirements are deleted.
Answer: B,C,E
NEW QUESTION 35
The company you advise wants to carry out the material availability check automatically in the production order at various points in time. Which of the following options would you recommend? (Choose two.)
- A. Goods receipt for a missing part
- B. Release of the production order
- C. Creation of the production order
- D. Goods receipt for the product produced with the order
- E. Confirmation of the operation that the materials being checked are assigned to
Answer: B,C
NEW QUESTION 36
......
SAP PP Certification Exam Details:
| Exam Name | SAP Certified Application Associate – Production Planning & Manufacturing with SAP ERP 6.0 EHP7 |
| Sample Questions | SAP PP Certification Sample Questions |
| Exam Code | C_TSCM42_67 |
| Exam Price | $550 (USD) |
| Reference Books | SCM240,SCM310, SCM300, SCM130, PLM114, TERP50, TERP01,SCM365 |
| Level | Associate |
| Number of Questions | 80 |
| Schedule Exam | SAP Training |
| Passing Score | C_TSCM42_67 - 63% |
| Duration | 180 mins |
SAP C_TSCM42_67 Exam Description:
The certification "SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7" verifies the knowledge in the area of Production for the consultant profile. This certificate proves that the candidate has a basic understanding within this consultant profile and can implement this knowledge practically in projects. The SAP Certified Application Associate can contribute to the success of the planning and implementation phases of the project in a mentored role and would typically have a maximum of three years experience in the solution area. Project experience should not be prerequisite for a competent and well trained candidate to pass this exam.
C_TSCM42_67 Exam Dumps PDF Guaranteed Success with Accurate & Updated Questions: https://www.2pass4sure.com/SAP-Certified-Application-Associate/C_TSCM42_67-actual-exam-braindumps.html